December 10, 2021 by Admin
During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering committee’s FIRST action?
- Require a revised business case.
- Approve the budget request.
- Provide appropriate training.
- Refer back to the project sponsor for resolution.