Which of the following tools is MOST appropriate for determining how long a security project will take to implement?

December 23, 2021 by Admin

Which of the following tools is MOST appropriate for determining how long a security project will take to implement?

  • Gantt chart
  • Waterfall chart
  • Critical path
  • Rapid Application Development (RAD)
Explanation:

The critical path method is most effective for determining how long a project will take. A waterfall chart is used to understand the flow of one process into another. A Gantt chart facilitates the proper estimation and allocation of resources. The Rapid Application Development (RAD) method is used as an aid to facilitate and expedite systems development.