A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts.
Which of the following is MOST likely the cause?
- There were not enough resources assigned to the project execution team.
- The PMO was not involved in project initiation and planning.
- Proper team-building activities were not performed when starting the project.
- A few major stakeholders were overlooked during project initiation and planning.