An IS auditor is conducting an interim review of an IT project. Which of the following would provide the MOST useful information regarding project performance?

December 16, 2021 by Admin

An IS auditor is conducting an interim review of an IT project. Which of the following would provide the MOST useful information regarding project performance?

  • Milestone review
  • Earned value analysis
  • Cost-benefit analysis
  • Function point analysis

Leave a Reply